หน้าแรก PTT  
Products & Services
Investor Relations
 
TH | ENG
Our LOGO
Background
Future Project
Recognition
Office Address
Research &
Technology Institute
Activities Services Testing Services
Internship
PTT Future Project
Home >About PTT > Future projects > Natural Gas Transmission Pipeline System   Print This Page 
 
 

Natural Gas Transmission Pipeline Project

 

On 19 June 2008, the cabinet approved the revision of the Master Plan for Natural gas Transmission Pipeline System Project (Revision 3/B.E. 2544-2554) to be used as a framework for investment of 165,077 million baht in the 14 projects of constructing Natural gas Transmission Pipeline System. The Master Plan optimizes the capabilities of PTT Natural Gas Transmission Pipeline, West and East Sides (including Pipeline from Nam Phong), rising from 3,680 million cubic feet per day (MMcf/d) (at actual heating value) at the end of 2007, to 6,980 MMcf/d (at actual heating value),together with three divided phases of investment and the further investment in the Offshore Gas Spur Lines Project

The First Phase of the Project:

  • The Project of Compressor Unit Installation at Block valve West 7 (BVW#7) in Kanchanaburi Province, was conducted to enhance the system’s capability in receiving and transmitting natural gas from Myanmar up to 1,300 MMcf/d. The project was complete in July 2006.
  • The Project of Natural Gas Transmission Pipeline, Sai Noi-North Bangkok and South Bangkok Power Plants, was executed to serve the demand of gas utilization under the Project of the Combined Heat Power Plant, North and South Bangkok , as well as that of private and transport sectors to reduce environmental pollution in Bangkok Metropolitan and Vicinity. In response to those projects, PTT planned to undertake a project to lay the 70-kilometer natural gas transmission pipeline, 30 inch in diameter, linking the Natural Gas Transmission Pipeline ,Ratchaburi-Wang Noi at Sai Noi District to South Bangkok Power plant. Meanwhile, the 10 km natural gas transmission pipeline, 20 inch in diameter, was laid, from Bang Yai to North Bangkok Power Plant with capacity 480 MMcf/d. The construction of Natural Gas Transmission Pipeline from Sai Noi to South Power Plant was complete and commenced operation in the fourth quarter of 2006. The project expanded to North Bangkok Power Plant and the Project of improvement of North Bangkok Power Plant undertaken by the Electricity Generating Authority of Thailand (EGAT) were scheduled to be simultaneously complete.scheduled to be simultaneously complete.
  • The Project of Stand-by Compressor Unit Installation was undertaken by PTT at the Region V Gas Pipeline Operation Division, Ratchaburi Province, to enhance stability and flexibility in transmitting natural gas from Myanmar to natural gas customers in the central region. The operational commencement took place in early May 2006.
  • The Project of Natural Gas transmission Offshore and Onshore Pipeline,No.3
  • The Project of PTT Riser Platform Construction (PRP) was complete in early 2008.
  • The Project of Laying Natural Gas transmission Offshore 418-kilometer Pipeline, 42 inch in diameter, from PTT Riser Platform to Rayong Province, , with optimum capacity in transmitting natural gas of 700 MMcf/d., rising to 1,900 MMcf/d, upon the installation of the Offshore Compressor Unit and operational commencement of the natural gas transmission in early 2007
  • The Project of Laying Natural Gas transmission Offshore 200-kilometer Pipeline, 42 inch in diameter, from Arthit Gas Field to PTT Riser Platform, with optimum capacity in transmitting natural gas of 1,500 MMcf/d. The project was finished and commenced operation in early 2008.
  • The Project of Laying Natural Gas transmission Onshore Pipeline, 36 inch in diameter, 110-kilometer in length, from Rayong Province linking in parallel with the Natural Gas Transmission Pipeline at the Compressor Station, Bang Pakong, with optimum capacity in transmitting natural gas of 400 MMcf/d., rising to 1,200 MMcf/d upon the installation of the Onshore Compressor Unit and operational commencement of the natural gas transmission in early 2006.

 

The Second Phase of The Project:

  • The Project of Laying Natural Gas transmission Offshore Pipeline, 42 inch in diameter, from JDA Gas Field to Arthit Gas Field, 95 kilometer in length, with highest capacity in transmitting natural gas of 1,000 MMcf/d. The project was complete and commenced operation in early 2008.
  • The Project of Laying Compressor Installation Unit of Natural Gas Transmission Offshore and Onshore Pipeline, No.3, to optimize the natural gas transmission’s capacity. The Onshore Compressor Unit was completely constructed and commenced operation in early 2007, while offshore one was expected to be complete by mid 2009.
  • The Project of Laying Natural Gas Transmission Onshore Pipeline, 36 inch in diameter, from Wangnoi District, Ayutthaya Province, to Khaeng Khoi District, Saraburi Province, 80 kilometer in length , with optimum capacity in transmitting natural gas of 510 MMcf/d, commenced operation at year-end of 2006.
  • The Project of Enroute Compressor Installation Unit to boost the capacity of Natural Gas Onshore Transmission from Wangnoi, as well as the Natural Gas Offshore Transmission’s capacity from the Gulf of Thailand to Ratchaburi Province and that of the Project of Natural Gas Transmission Pipeline, Sai Noi-South Bangkok / North Bangkok, expecting to be complete by early 2010
  • The Project of Natural Gas Transmission Onshore Pipeline, 42 inch in diameter, from Rayong Province to Wangnoi District, Ayutthaya Province, 300 kilometer in length, with the highest capacity in transmitting natural gas of 1,400 MMcf/d, expecting to commence operation in early 2011.

The Third Phase of The Project:

  • The Project of Compressor Installation on Natural Gas Transmission Pipeline System, West Side, to optimize the capability of Natural Gas Transmission Pipeline System, West Side, expecting to be complete in early 2012

Further Investment in the Offshore Gas Spur Lines Project :

  • The Project of Offshore Gas Spur Line System, 18 inch in diameter, from the annex of Arthit Gas Field, North, to the Natural Gas Transmission Offshore Pipeline System, No.3, 40-kilometer in length, with the highest capacity totally 150 MMcf/d, expecting to be complete in mid 2008
  • The Project of Offshore Gas Spur Lines , 24 inch in diameter, from the annex of Chevron gas Field to the Natural Gas Transmission Offshore Pipeline System, No. 3, 45-kilometer in length, with the highest capacity totally 330 MMcf/d, expecting to be finished in late 2010
  • The Project of Offshore Gas Spur Lines , 24 inch in diameter, from the annex of Bongkot Gas Field to the Natural Gas Transmission Pipeline System, No. 3, 50- kilometer in length, with the highest capacity totally 200 MMcf/d, expecting to be complete in early 2011
  • The Project of Offshore Gas Spur Lines , 24 inch in diameter, from the annex of Pailin Gas Field to the Natural Gas Transmission Pipeline System, No. 3, 40-kilometer in length, with the highest capacity totally 200 MMcf/d, expecting to be complete in early 2012
   
   
 
 
 
 
 Copyright 2008 PTT Plc. All right reserved
Home
FAQ/Contact Us
Career
Site Map
PTT E-mail
PTT Group KM
PTT Group Event Report
PTT Group OIM